Taiwan | 2021-04-28
Jan De Nul has commenced the turbine installation at Taiwan Power Company’s Changhua Phase 1 offshore wind project after the winter break.
The company’s jack-up vessel Taillevent installed the sixth Hitachi 5.2 MW turbine this week at the site located off the coast of Fangyuan in Central Western Taiwan.
Taillevent erected the first of the total of 21 turbines with a downwind rotor at Changhua Phase 1 in September 2020.
The consortium of Jan De Nul and Hitachi secured the contract for the 109.2 MW offshore wind farm back in February 2018.
Jan De Nul is responsible for the design, fabrication, and installation of the foundations and turbines, supply and installation of the onshore and offshore cables, as well as for upgrading the substation.
Hitachi is in charge of manufacturing, assembly, O&M, and other works related to the turbines.
Author: https://www.offshorewind.biz/
Photo: Jan De Nul
Taiwan | 2022-05-04
Currently, we have several vacancies for Personnel on Dredgers and Barges. Open positions:
Read moreTaiwan | 2022-04-05
We are urgently looking for experienced Riggers for a few projects.
Read moreTaiwan | 2022-04-01
We are urgently looking for 2x Rigger Foreman and 2x Riggers with Lifting experience.
Read moreTaiwan | 2022-03-24
We are very urgently looking for AB, Welder & Stewards for the DP2 Fallpipe vessel.
Read moreTaiwan | 2022-03-14
We are looking for a Riggers, one rigger needs to have a Scaffolder certificate and another Crane Operator certificate.
Read moreTaiwan | 2022-03-02
We urgently need Riggers with cable pay experience. The first batch starts on 04 April & the second one on 19 May.
Read moreTaiwan | 2021-12-15
We are looking for experienced ROV Trencher Operators for projects in Taiwan.
Read moreTaiwan | 2021-10-27
We are urgently looking for Crane Operators that have 5000T experience for long-term projects, on Jack-Up and Heavy Lift Installation vessels.
Read moreTaiwan | 2021-09-15
We are urgently looking for Tensioner Operator and also for Crane Operator.
Read moreTaiwan | 2021-08-18
Boskalis has completed the installation campaign of 48 pin piles for the 600MW Changfang & Xidao offshore Changfang & Xidao (CFXD) offshore wind farm phase one-off Taiwan. Boskalis’ crane vessel Bokalift 1 was used for the campaign which kicked off in early July. CFXD is located 15km off the coast of Changhua County in Taiwan. ...
Read moreTaiwan | 2021-08-03
Siemens Gamesa’s offshore wind nacelle assembly facility in Taichung, Taiwan has assembled its first nacelle. This marks the first time a Siemens Gamesa offshore turbine nacelle has been assembled outside Europe. The construction work on Siemens Gamesa’s assembly facility in Taichung Harbor started in March 2020. The parcel of land being developed in Taiwan measures ...
Read moreTaiwan | 2021-07-20
We are looking for an experienced SShift Supervisor; Rigger Foreman & Deck Foreman for the Heavy Lift Crane vessel. Details: Vessels: Heavy Lift Crane vessel; Rigger Foreman start: approx. 26/07/2021; Deck Foreman start: approx. 01/09/2021; Location: Taiwan; Duration: approx. 10 weeks; Requirements: Relevant to the position Offshore certificates; Valid STCW certificates; Valid MLC medical; Experience ...
Read moreTaiwan | 2021-06-30
Eager.one has produced a Jacket Lifting Tool (JLT) specially made for the installation of jacket foundations that will be carried out by Boskalis on a Taiwanese project.
Read moreTaiwan | 2021-06-04
We are looking for an experienced Electrician and Second Engineer unlimited for the Rock dumping vessel
Read moreTaiwan | 2021-05-27
We are searching for experienced 2nd Officer/DPO, Crane Operator, 2nd Engineer and 3rd Engineer for long-term project in Taiwan
Read moreTaiwan | 2021-05-10
We are urgently looking for experienced Shift Foreman for Construction Support Vessel. Project located in Taiwan.
Read moreTaiwan | 2021-05-07
PanGeo Subsea is working with Jan De Nul in Taiwan on a cable depth of burial survey at the Formosa 2 offshore wind farm, with PanGeo’s sub-seabed 3D acoustic imaging technology being used for the campaign. According to the subsea imaging technology company, which delivered its Sub Bottom Imager (SBI) for the work, the survey ...
Read moreTaiwan | 2021-05-07
We are urgently looking for Second Engineer experienced with DP vessels, for Pipe burying vessel
Read moreTaiwan | 2021-05-06
We are urgently looking for Commissioning Supervisor for project located in Taiwan
Read moreTaiwan | 2021-04-19
We are urgently looking for Rigger Foreman for Heavy Lift vessel, project located in Taiwan
Read moreTaiwan | 2021-04-15
We are urgently looking for Rigger with Cable Pull and Scaffolding experience for the middle of June
Read moreTaiwan | 2021-03-25
We are urgently looking for Rigger with Cable Pull and Scaffolding experience for the beginning of May
Read moreTaiwan | 2021-03-08
We are urgently looking for available 2nd Officer DPO with Taiwan visa for Offshore Wind farm project
Read moreTaiwan | 2021-03-02
We are urgently looking for AB, Fitter, Deck Foreman and Equipment/Tension Operator for Cable layer, project located in Taiwan
Read moreTaiwan | 2021-02-12
We are looking for experienced Tower Shift Supervisor for Offshore Support vessel in the beginning of March
Read moreTaiwan | 2021-02-12
We are looking for experienced Shift Supervisor for Offshore Support vessel in the beginning of March
Read moreTaiwan | 2021-02-02
For Onshore project in April we are looking for experienced Site Supervisor for Beach pull operations
Read moreTaiwan | 2021-01-28
We are urgently looking for Electrician for Pipe burying vessel
Read moreTaiwan | 2021-01-25
Pile-driving specialist MENCK has won a contract to support Boskalis with the foundation piling activities on the Changfang and Xidao offshore wind farm in Taiwan. This involves the piling of 186 pin piles for the 62 three-legged jacket foundations being installed over two campaigns in 2021 and 2022 in water depths of up to 40 ...
Read more